Every GRP installation combines product tolerance, fabrication tolerance, support-frame accuracy and site movement. If those allowances are not coordinated, panels can lose bearing, joints can close up and installers may be tempted to force or recut components.
In brief
- Do not assign the entire tolerance to the final installer.
- Measure the support frame as built before releasing critical fabrication.
- Protect minimum bearing and safe edge gaps at worst-case tolerance.
- Use slotted or adjustable details only where their structural effect is assessed.
Tolerance stack
| Source | Examples |
|---|---|
| Product manufacture | Panel length, width, thickness and profile straightness |
| Fabrication | Cut size, squareness, hole position and assembly |
| Support frame | Opening size, level, parallelism and bearing width |
| Installation | Setting out, clearance, fixing position and access |
| Service | Temperature, movement, settlement and replacement |
Drawing checklist
- Reference datums and surveyed opening dimensions.
- Critical versus non-critical dimensions.
- Minimum bearing and maximum safe gaps.
- Hole type, size, edge distance and positional tolerance.
- Panel joints, removable areas and match marks.
- Inspection method and disposition for non-conformance.
GRP should not be forced into an undersized frame or left with inadequate support because nominal dimensions appeared to match. Resolve the tolerance budget before the cut list is approved.
Frequently asked questions
Can GRP panels be trimmed on site?
Often, with suitable tools, PPE and edge finishing, but the remaining geometry and support must stay compliant.
Should every joint be tight?
No. Appropriate clearances allow installation and movement while maintaining safe gaps and bearing.
Can slotted holes solve alignment problems?
Only where washer coverage, bearing, movement and connection capacity are verified.
Approve the tolerance budget with the cut list
Send surveyed dimensions, supports, joints and critical interfaces for fabrication planning.